← All topics👷 Men · Days · HoursMaths
Time & Work · Topic 3 of 6

👷 Men · Days · Hours

1 exam question type, fully solved

“If 10 men build a wall in 6 days, how long do 15 men take?” These are men–days problems. They all bend to one master formula — no long thinking, just plug into the chain rule.

The M·D·H/W chain rule

The total effort a group puts in is (number of men) × (days) × (hours per day), and that effort is shared across the amount of work . For two situations doing the same kind of work, this stays balanced:

where = men, = days, = hours/day, = amount of work. Drop any quantity that is not mentioned (if hours and work are not stated, set and ).

• How to use it: write everything you know on the left for situation 1, everything for situation 2 on the right, put the unknown as a letter, and cross-multiply.

• Example: 10 men, 6 days. Find days for 15 men. gives days.

Why it works: more men ⇒ fewer days (inverse), more work ⇒ more days (direct). The formula bakes both in, so you never have to decide “multiply or divide” by hand.

🧱Time & Work LabTotal work = LCM units — no fractions
M₁·D₁·H₁ / W₁=M₂·D₂·H₂ / W₂
Situation 1 — everything known
Men M₁
Days D₁
Hrs/day H₁
Work W₁
Situation 2 — find:
Men M₂
Days D₂
?
Hrs/day H₂
Work W₂
Substitute: (10 × 6 × 1) / 1 = (15 × ? × 1) / 1 Cross-multiply: ? = (10 × 6 × 1 × 1) ÷ (1 × 15 × 1) = 60 ÷ 15
D₂ = 4 days

12 men finish in 8 days. For 16 men: , so days.

📝Practice Questions

Q140 men complete a work in 18 days. After 6 days, 10 men leave. In how many days is the remaining work completed?

Q220 workers can finish a job in 30 days. 5 more workers join after 10 days. In how many days is the whole job completed?

Q3A work is completed by 35 workers in 30 days. If 5 workers leave after every 10 days, in how many days is the work completed?

📚

Real exam questions — Men · Days · Hours

2 question types · 8 solved examples from real SSC papers

Treat a job as a fixed pile of man-days: men times days (times hours/day) stays constant, so when one factor changes the others adjust in inverse proportion.

How to solve this type
Write the total work as M×DM \times D man-days. Put the knowns on each side, the unknown as a letter, then cross-multiply. More men means fewer days, so the two move in inverse ratio.

15 workers complete a work in 20 days. How many workers are needed to complete it in 10 days?

A25B35C20D30

8 men can complete a work in 15 days. In how many days will 12 men complete it?

A8 daysB10 daysC6 daysD12 days

18 men finish a work in 20 days. In how many days will 24 men finish the same work?

A12 daysB15 daysC18 daysD10 days

A work can be completed by 35 workers in 30 days. How many workers are needed to finish it in 21 days?

A48B45C50D42