Time & Work · Topic 1 of 6

🛠️ Work & Time Basics

2 exam question types, fully solved

In a time & work sum the trap is fractions. If A finishes a job in 12 days, A does of it each day; if B takes 6 days, B does a day. Adding is slow. There is a faster way that kills the fractions completely.

The LCM method — make “total work” the LCM of the times

Instead of calling the job , call the total work the LCM of all the given times. Then every rate becomes a whole number, so you just add and divide.

• Step 1. A takes 12 days, B takes 6 days. Total work units.

• Step 2. Rate . So A does unit/day, B does units/day.

• Step 3. Working together they do units/day.

• Step 4. Time together days.

Two-worker shortcut: if A takes days and B takes days, together they take days (product over sum). Here days.

Fraction of work done in days . If A finishes in 12 days, in 3 days A has done of it, and is left.

🧱Time & Work LabTotal work = LCM units — no fractions
A finishes in (days)
B finishes in (days)
Total work = LCM(12, 15) = 60 units
A's speed (12 days alone)60 ÷ 12 = 5 units/day
B's speed (15 days alone)60 ÷ 15 = 4 units/day
Together, per day5 + 4 = 9 units/day
Together they finish in 60/9 = 6 2/3 days
Call the whole job 60 units (the LCM), not "1". Every speed becomes a whole number — that is the entire trick. Time together = total work ÷ combined speed = 60 ÷ 9 = 60/9 = 6 2/3 days.

A does a job in 10 days, B in 15 days. Total work = LCM(10,15) = 30; rates 3 and 2; together days.

📝Practice Questions

Q1A can do a work in 12 days and B in 15 days. Working together, they finish in:

Q2A completes 60% of a work in 9 days. How many days are needed to finish the remaining 40%?

Q3A, B and C do work in the ratio 2:3:5. The total payment is ₹12,000. B's payment is:

📚

Real exam questions — Work & Time Basics

2 question types · 8 solved examples from real SSC papers

Work-and-time basics: turn each person's time into a work-rate, add the rates to combine workers, and scale a fraction of work up to full time or split wages.

How to solve this type
Convert times into work-rates and ADD the rates, never the days. Fast default: let total work = LCM of the given times, then each rate = total ÷\div that person's time. Add the rates and divide total work by the combined rate. For exactly two workers you can also use the shortcut combined time =a×ba+b=\dfrac{a\times b}{a+b} (product over sum).

A can do a work in 12 days and B in 15 days. Working together, they finish in:

A7 daysB8 daysC6⅔ daysD5 days

Surjeet alone finishes a work in 8 days; Manjeet alone in 6 days. Together they finish in:

A3.5 daysB4 daysC3 daysD24/7 days

X can type 8 pages in 3 minutes; Y can type 3 pages in 5 minutes. Together in 15 minutes they type:

A42 pagesB46 pagesC49 pagesD40 pages

A and B together finish a work in 10 days. A alone finishes in 15 days. B alone takes:

A30 daysB18 daysC25 daysD20 days